Use Your Holiday Shutdown for Electrical Maintenance: A Year-End Checklist

Written by Alyssa Rice | Nov 25, 2026, 7:30:00 PM

Before the shutdown, scan equipment under normal operating load to prioritize repairs. During the outage, follow your documented lockout/tagout procedure and have qualified personnel verify absence of voltage at each point of work. After restart, rescan repairs under normal operating load, update condition ratings, and schedule follow-up work.

Download the printable Holiday Shutdown Electrical Maintenance Checklist

For some plants, the year-end shutdown is one of the few chances to take a busy line offline. Late November is a good time to pull up the last inspection report with the people who’ll do the work. If a repair needs a part you don’t stock or a contractor who books up in December, you still have time to get it on the schedule.

What Should You Do Before The Shutdown?

Start your holiday shutdown maintenance checklist with the equipment that’s still running its usual schedule. Once production slows down, a connection that ran hot all shift can look ordinary on an infrared image.

  • Run an infrared thermography scan under normal operating load. Have qualified personnel perform the scan using the electrical safe work practices and PPE appropriate to the task. Record the asset, connection, and load when the image is taken. If one phase runs warmer than the others, check whether the loads are comparable. Our guide explains how to interpret temperature differences in panels and switchgear.
  • Turn scan findings into a prioritized work list. On each work order, identify the equipment, mark the exact connection, and name the person responsible. A photo marked “outgoing feeder, phase B” gives the outage crew a more useful starting point than “panel running hot.” Escalate urgent findings as soon as they’re identified.
  • Review NFPA 70B condition ratings and flag overdue maintenance. Under the 2023 criteria, equipment that missed the previous two maintenance cycles is classified as Condition 3. NFPA’s published development table for the 2026 edition lists thermography intervals of 12 months for Conditions 1 and 2 and six months for Condition 3. Review the NFPA 70B maintenance intervals alongside your facility’s electrical maintenance program and applicable edition.
  • Confirm documented lockout/tagout (LOTO) procedures are current. Has anyone added a feed or changed a disconnect since the last outage? Check the procedure against the equipment the crew will actually service. Use the planning meeting to confirm when lockout/tagout is required and who coordinates it.
  • Check test instruments and PPE. Confirm that instruments are adequately rated and working and that the crew has the personal protective equipment identified for the task.
  • Order spare parts and confirm contractor schedules. Check the replacement part number against the equipment and confirm when the contractor can be on site.

What Should You Do During The Shutdown?

Even with the line stopped, conductors inside a cabinet can still be energized. Before anyone starts work that requires de-energized equipment, qualified electrical personnel must establish and verify an electrically safe work condition under the facility’s documented procedures.

  • Lock out every energy source according to your documented LOTO procedure. Account for stored energy and possible backfeed. Coordinate isolation and verification with the crew responsible for the equipment. Review the seven steps in a LOTO procedure with incoming contractors so everyone knows who controls each isolation point.
  • Test for absence of voltage at each point of work. Under NFPA 70E 120.6(7), the portable-instrument method calls for an adequately rated test instrument to check each phase conductor or circuit part, both phase-to-phase and phase-to-ground. See what an absence of voltage test verifies.
  • Verify the test instrument on a known voltage source before and after each test. The second check confirms that the instrument still functions after the absence-of-voltage test.
  • Do not use a non-contact tester for this test on systems rated 1000 volts or less.
  • Clean, inspect, and torque connections per manufacturer instructions. Use the instructions for the specific assembly to determine which connections need attention and the applicable torque values.
  • Complete scheduled insulation resistance and protective device testing. Coordinate any test that introduces voltage with the other crews and follow the applicable test procedure.
  • Inspect components flagged by the scan and replace any confirmed to be damaged. Record what the crew found and replaced.
  • Make sure every authorized worker performing the work, including contractors, applies their own lock. For group lockout, coordinate personal locks through the facility’s group lockout procedure from the start of the job, including during crew or shift changes.

 

What Should You Do After Restart?

Before restart, qualified personnel complete the facility’s return-to-service checks and coordinate with operations. If the line starts up slowly, an hour into the first shift may be too early to tell whether a repair worked. Find out when the line will be back at its usual load and book the rescan for then.

  • Remove locks and re-energize according to your procedure. Before restoring power, follow site requirements for clearing personnel, tools, and temporary devices, removing personal locks, and notifying affected workers.
  • Rescan repaired connections under normal operating load. Compare the same point with the original image and record the load for both readings. That way, a lighter production shift won’t be mistaken for a successful repair.
  • Update condition ratings and NFPA 70B maintenance records. Attach the before-and-after images, test results, repair details, and reasons for any change in equipment condition.
  • Log open items and schedule follow-up work. If a rescan is still due when the crew leaves, make sure the next shift knows who’s doing it and when.
  • Set the 2027 maintenance schedule. Use the updated condition assessments and the facility’s maintenance program to set the next inspection and testing dates for each asset.

How Do You Keep Connections From Heating Up Again Before Next Year?

Start with the cause of the hot spot. Once the crew has corrected it, the December rescan gives you a baseline. If that same feeder lug shows up warm again in February, you’ll want to know whether its temperature has been creeping up for weeks or just changed on the last shift.

A connection that keeps turning up on inspection reports is a good place to consider using both IR thermography and continuous thermal monitoring. The GraceSense HSM 600 tracks temperature at selected connections in low-voltage equipment and can alert the team when a reading crosses a configured threshold. Your past work orders can help you choose which points to monitor first. For a closer look at what happens at the joint, see why MCC and PDU connections develop hot spots.

Frequently Asked Questions

When should you do an IR scan around a shutdown?

 Scan before the shutdown while equipment is under normal operating load. After restart, rescan the repaired connections once normal load returns. Record the load and location both times so the team can compare the repair with the original finding. 

Do you still need lockout/tagout during a plant shutdown?

 Yes, when the servicing task requires hazardous energy control. A plant-wide shutdown does not establish isolation at an individual asset. Follow the documented LOTO procedure and have qualified electrical personnel verify absence of voltage at each point of electrical work. 

What electrical maintenance needs a de-energized outage?

 Typical examples include internal cleaning, servicing connections, replacing damaged lugs or breakers, and scheduled insulation resistance or protective device testing. Identify which tasks require isolation or a separate controlled test setup using the equipment manufacturer’s instructions and facility procedures. 

How do you document shutdown work for NFPA 70B?

 Record the asset ID, date, findings, work performed, and test results in the electrical maintenance record. Include the post-restart verification, updated condition assessment, and next scheduled maintenance date. Assign an owner to any item that still needs follow-up. 

 

Get Your Holiday Shutdown Checklist

Use this checklist alongside your facility’s documented procedures, manufacturer instructions, and the applicable editions of NFPA 70E and NFPA 70B.

Bring the printable Holiday Shutdown Electrical Maintenance Checklist to your next outage planning meeting. There’s room to identify the equipment, record the shutdown dates, and carry open items into the next shift.

Have a safe Thanksgiving, and subscribe to the Humpday Blog for more electrical maintenance and safety resources.

Download the printable Holiday Shutdown Electrical Maintenance Checklist

Stay SAFE, and have a GREAT week!